Provide one set of the following for initial review:
1. Plan on sheet
2. Building, parking lot, etc outline with all utilities shown
3. Sanitary Sewer Service
a. Length/slope of service line shown
b.Cleanouts shown at change in directions
c. Point of connection shown
d. Dimension form nearest manhole shown
e. Grease interceptor shown
f. Plumbing plan provided
g.Kitchen fixture plan provided
h.Grease interceptor sizing calculations provided
I.Details provided:
- Cleanout
4. Water Service
a.Service line and fire sprinkler line shown
b. Points of connection shown
c.Dimension form nearest valve, fire hydrant shown
d. Meter pit location shown
e.
Inside meter within 60' of water main(Inside meters are no longer allowed in Denver Water service areas)
f.Details provided:
- Service line
- Meter pit
- Fire sprinkler line
- Typical trench
For final submittal and approval the District requires:
- Two sets of the water/fire line plan
- Three sets of the sanitary sewer line plan
- One electronic file (Auto-CAD)
Download - Service Line Checklist.pdf